Bolivarian Government carries out comprehensive maintenance at Siberia substation


Courtesy Internet

Published at: 17/05/2025 12:50 PM

Workers from the National Electric Corporation (CORPOELEC) carried out comprehensive maintenance work at the Siberia substation, benefiting 21,000 inhabitants of the Uribante municipality in the state of Táchira.

During the work carried out by the state generation management, insulation tests were carried out on the 1 MVA power transformer and the good functioning of the coils inside the equipment was verified, with the purpose of guaranteeing the electricity supply to the population of the mountain area.

With these works, CORPOELEC optimized the operation of the Siberia 34.5 kV circuit, strengthening energy transmission in the Araguaney, La Onda, Santa Rosa, Pregonero, Siberia, Campamento La Trampa and Caparo sectors of the Uribante municipality.

the workers carry out these maintenance maneuvers at the substation on a constant basis, with the purpose of continuing to keep in good condition the equipment and electrical elements generated and distributed the service in the area.