More than 13,000 Guaireños benefited from corrective maintenance in electrical substations
Photo: CORPOELEC
Published at: 25/08/2025 04:29 PM
The National Electric Corporation (CORPOELEC) carried out preventive and corrective maintenance work on electrical installations on the coastal axis of the state of La Guaira, benefiting more than 13,000 users in the Naiguatá and Caruao parishes.
The technical deployment included interventions at the Anare, Los Caracas, Todasana, La Sabana and Chuspa substations, as well as the 30 kV transmission line in Los Caracas, with the purpose of strengthening the reliability of the electrical system.
These maneuvers, according to a press release from CORPOELEC, consisted of the review and diagnosis of power equipment, electrical tests, maintenance and lubrication of components, cleaning, technical adjustments and repair of transmission conductors.