They estimate placing more than 100,000 tons of asphalt on Trujillanas roads

Four important bridges located in different sectors are also expected to recover this year.
Photo: Internet

Published at: 17/01/2025 04:23 PM

Through the Road Rehabilitation Plan being implemented in the state of Trujillo, more than 100,000 tons of asphalt are planned to be installed during 2025, said the governor of the entity, Gerardo Márquez.

Through his program Háblame Gerardo, broadcast on Paisana 92.5 FM, the president stressed that this plan has been carried out for three years, with which important road axes have been recovered in the 20 municipalities that make up this entity located in the Venezuelan Andean region.

In addition, as reported by the Venezuelan News Agency (AVN), four important bridges located in different sectors are also expected to recover this year.

In this regard, Márquez indicated that the Santa Rosa de Jiménez bridge, in the municipality of Pampanito, has already been recovered. He also said that among the roads that will be impacted through this rehabilitation plan is the Pampan-La Libertad axis.

Meanwhile, the Asphalt Company (Emastru), since the beginning of this year, has placed 1,150 tons of asphalt, dealing with patching and sorting tasks in sectors of the municipalities of Boconó, Escuque, Monte Carmelo, San Rafael de Carvajal, Sucre Urdaneta and Valera.

In addition, more than 6,600 linear meters of brothels have been painted on 13th Avenue in Valera.

The demarcation of 36,000 linear meters was also carried out in towns in the municipalities of Candelaria and Pampanito.

Likewise, 1,200 linear meters of road sides were cleaned and 850 cubic meters of sediment removed from the Round Tree to Piedra Parada, on trunk 007.

Mazo News Team

Share this news: