CORPOELEC maintained circuits in Valencia to benefit more than 170,000 people
Photo: CORPOELEC
Published at: 23/09/2025 12:47 PM
The National Electric Corporation (CORPOELEC) carried out comprehensive maintenance in the municipality of Valencia, with the objective of strengthening the operation of distribution circuits and ensuring a more stable electricity service for more than 170,000 users in the state of Carabobo.
According to a press release from CORPOELEC, the tasks included the installation of two reconnectors on the Soublette I and Viñedo circuits, as well as the assembly of two sets of disconnectors on the Racetrack circuit.
At the same time, 171 meters of conductor were placed on the Castillo 2 circuit and lightning rods and terminal cups were installed, actions that directly contribute to the reliability of the system.
These improvements have a positive impact on residential, commercial and industrial areas, reducing the risk of interruptions and extending the useful life of equipment.
Mazo News Team